"ROSSETI" electricity company completed the main stage of the integrated reconstruction of a double-circuit 220 kV overhead line "Lipetsk - Kazinka" with a length of over 19 km.
During the reconstruction all structures and equipment (supports, foundations) were completely replaced and tension of the wire and installation of a lightning protection cable – carried out.
The cost of works amounted to more than 710 million rubles. The project will provide an additional 239 MW of power to residents of the Lipetsk SEZ.
Thus, the volume of power generated by the Lipetsk SEZ will increase from 28 to 267 MW.
As of today, there are 29 enterprises (including those under construction) on Gryazi site of the Lipetsk SEZ that consume energy.
The necessary power supply capacity for their functioning is provided by "SEZ"PS 110/10/10 kV and "Kazinka" PS 220/110/10 kV, commissioned in 2007 and 2017, respectively.
Currently, the SEZ site is developed by 80%, and new residents are offered a connection to all kinds of resources necessary for each enterprise in accordance with the most modern standards, including telecommunications and dispatching.