PLC “ROSSETI” has begun the main stage of complex reconstruction of the 220 kV double circuit line “Lipetskaya – Kazinka” with a length of more than 19 km.
All construction steelwork and equipment – supports, foundations, wires, lightning protection cable – will be replaced. The cost of work exceeds 710 million rubles and will be completed in 2021.
The aim of the project is to provide additional 239 MW of capacity to tenants. Thus, the volume of capacity issued by the special economic zone Lipetsk will grow from 28 up to 267 MW.
To date, 28 enterprises (including those under construction) consume energy on Gryazinsky site of the SEZ Lipetsk.
New residents on Gryazinsky industrial site are offered all types of necessary resources in accordance with the best modern standards, including telecommunications and dispatching.